MISO-J2450
100 MW storage in Tippecanoe, IN · In queue since September 2022 · Proposed COD October 2026
100 MW
Capacity
1
Components
Battery
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-10-31
MISO-J2450 is a proposed 100 MW battery storage project located in Tippecanoe County, Indiana. The project, which is in the Duke Energy Indiana service area, entered the Midcontinent Independent System Operator (MISO) interconnection queue on September 15, 2022. Its proposed commercial operation date is October 31, 2026.
The project's interconnection status is currently in the Cluster Study phase. The point of interconnection is the Westwood 345 kV substation.
Generated from interconnection queue and public data sources
State
IN
County
Tippecanoe
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
DUKE ENERGY INDIANA
Entity
MISO
Service Type
—
Point of Interconnection
WESTWOOD 345 KV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CONS.CC.JAXSON
- POI Substation
- Westwood Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2450