MISO-J2456
100 MW hybrid in Phillips, AR · In queue since September 2022 · Proposed COD March 2027
100 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-03-01
MISO-J2456 is a proposed 100 MW hybrid solar and battery energy storage project located in Phillips County, Arkansas. The project, which consists of 100 MW of solar capacity, is in the Midcontinent Independent System Operator (MISO) interconnection queue. Its queue entry date is September 14, 2022, with a proposed commercial operation date of March 1, 2027. The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)".
The proposed project is interconnected to the Entergy Arkansas utility system at the AECC AUBREY-RITCHIE SES SWITCHYARD 230 KV point of interconnection.
Generated from interconnection queue and public data sources
State
AR
County
Phillips
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY ARKANSAS
Entity
MISO
Service Type
—
Point of Interconnection
AECC AUBREY-RITCHIE SES SWITCHYARD 230 KV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.