MISO-J2469
300 MW storage in Linn, IA · In queue since September 2022 · Proposed COD October 2027
300 MW
Capacity
1
Components
Battery
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2027
Total Duration
5y 1m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-01
MISO-J2469 is a proposed 300 MW battery storage project located in Linn County, Iowa. The project, which consists entirely of battery storage, is in the Midcontinent Independent System Operator (MISO) interconnection queue. Its queue entry date is September 12, 2022, and it has a proposed commercial operation date of October 1, 2027. The interconnection status is currently in the Cluster Study phase.
The proposed project is interconnected to the ITC Midwest utility and its point of interconnection (POI) is the Sub K (Tiffin)-Duane Arnold 345kV substation.
Generated from interconnection queue and public data sources
State
IA
County
Linn
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC MIDWEST
Entity
MISO
Service Type
—
Point of Interconnection
Sub K (Tiffin)-Duane Arnold 345kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2469