MISO-J2472
200 MW storage in Sullivan, IN · In queue since September 2022 · Proposed COD May 2027
200 MW
Capacity
1
Components
Battery
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2027
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-05-07
MISO-J2472 is a proposed 200 MW battery storage project located in Sullivan County, Indiana. The project, under development within the MISO region, is being pursued by Hoosier Energy. It consists solely of battery storage, with a total capacity of 200 MW.
The project entered the MISO interconnection queue on September 15, 2022, with a proposed commercial operation date of May 7, 2027. Its interconnection status is currently in the Cluster Study phase, and the point of interconnection is the Gibson Station - Merom (HED) 345.0kV line.
Generated from interconnection queue and public data sources
State
IN
County
Sullivan
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
HOOSIER ENERGY
Entity
MISO
Service Type
—
Point of Interconnection
Gibson Sta - Merom (HED) 345.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.