MISO-J2475
200 MW storage in Monroe, MI · In queue since September 2022 · Proposed COD September 2026
200 MW
Capacity
1
Components
Battery
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4 years
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-30
MISO-J2475 is a proposed 200 MW battery storage project located in Monroe County, Michigan. The project, interconnected with ITC, entered the MISO queue on September 15, 2022, with a proposed commercial operation date of September 30, 2026. Its interconnection agreement status is currently listed as "In Progress (unknown study)".
The development project consists solely of battery storage, with a total capacity of 200 MW. It is currently listed as active within the MISO interconnection queue.
Generated from interconnection queue and public data sources
State
MI
County
Monroe
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC
Entity
MISO
Service Type
—
Point of Interconnection
Toll Rd 120kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2475