Project MISO-J2478 — Project Summary

Queue ID
MISO-J2478
Capacity
700 MW
Technology
Solar
Status
active
Location
Craighead, AR
Region
MISO
Developer
IA Status
In Progress (unknown study)

MISO-J2478

MISO-J2478BetaActiveSolarMISOLBNL + Live

700 MW generation in Craighead, AR · In queue since September 2022 · Proposed COD October 2026

700 MW

Capacity

1

Components

Solar

3y 8m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection

Total Duration

4y 1m

In Study38%
Queue EntrySep 14, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-10-31

About

MISO-J2478 is a proposed solar generation project located in Craighead County, Arkansas, within the Midcontinent Independent System Operator (MISO) region. The project, with a total capacity of 700 MW, is being developed by an unknown entity and is interconnected with Entergy Arkansas. The project entered the MISO interconnection queue on September 14, 2022, with a proposed commercial operation date of October 31, 2026.

The interconnection agreement (IA) status for MISO-J2478 is currently "In Progress (unknown study)". The point of interconnection (POI) is the INDEPENDENCE-ISES - POWERLINE ROAD 500.0kV. The project has appeared in recent news.

Generated from interconnection queue and public data sources

Project Details

State

AR

County

Craighead

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

ENTERGY ARKANSAS

Entity

MISO

Service Type

Point of Interconnection

INDEPENDENCE-ISES - POWERLINE ROAD 500.0kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
MISO
Trading Hub
ARKANSAS.HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.