MISO-J2485
200 MW generation in Livingston, MI · In queue since September 2022 · Proposed COD November 2025
200 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 2m
Schedule
6 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-11-01
MISO-J2485 is a proposed solar generation project with a total capacity of 200 MW, located in Livingston County, Michigan. The project is interconnected within the Midcontinent Independent System Operator (MISO) region and is in the interconnection queue under queue ID MISO-J2485. The queue entry date is September 14, 2022, with a proposed commercial operation date of November 1, 2025. The interconnection agreement status is currently "In Progress (unknown study)".
The project, which is being developed within the ITC utility territory, consists of 200 MW of solar photovoltaic generation. The point of interconnection is the Madrid - Blackfoot 345kV line.
Generated from interconnection queue and public data sources
State
MI
County
Livingston
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC
Entity
MISO
Service Type
—
Point of Interconnection
Madrid - Blackfoot 345kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2485