MISO-J2490
125 MW generation in Tuscola, MI · In queue since September 2022 · Proposed COD November 2025
125 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2025
Total Duration
3y 2m
Schedule
6 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-11-01
MISO-J2490 is a proposed solar generation project located in Tuscola County, Michigan, with a total capacity of 125 MW. The project, interconnected with ITC, entered the MISO interconnection queue on September 14, 2022, and has a proposed commercial operation date of November 1, 2025. Its interconnection status is currently in the Cluster Study phase.
The project consists of 125 MW of solar photovoltaic generation. The point of interconnection is the Tuscola-Arrowhead 120kV Transmission Line.
Generated from interconnection queue and public data sources
State
MI
County
Tuscola
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC
Entity
MISO
Service Type
—
Point of Interconnection
Tuscola-Arrowhead 120kV Transmission Line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM