MISO-J2496
400 MW storage in White, IN · In queue since September 2022 · Proposed COD March 2026
400 MW
Capacity
1
Components
Battery
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
3y 6m
Schedule
2 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-03-07
MISO-J2496 is a proposed 400 MW battery storage project located in White County, Indiana. The project, which consists entirely of battery storage, is in the Midcontinent Independent System Operator (MISO) interconnection queue. Its queue entry date is September 13, 2022, and the proposed commercial operation date is March 7, 2026. The project's interconnection status is currently in the Cluster Study phase. Northern Indiana Public Service Company is the utility associated with the project.
The proposed project would interconnect at the Reynolds 345 kV Substation.
Generated from interconnection queue and public data sources
State
IN
County
White
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN INDIANA PUBLIC SERVICE COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Reynolds 345 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- Reynolds Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2496