MISO-J2523
250 MW generation in Independence, AR · In queue since September 2022 · Proposed COD November 2026
250 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-11-01
MISO-J2523 is a proposed solar generation project with a total capacity of 250 MW, located in Independence County, Arkansas. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of September 14, 2022. The proposed commercial operation date is November 1, 2026.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The designated point of interconnection (POI) is the INDEPENDENCE-ISES 500kV Substation, and the interconnecting utility is Entergy Arkansas.
Generated from interconnection queue and public data sources
State
AR
County
Independence
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY ARKANSAS
Entity
MISO
Service Type
—
Point of Interconnection
INDEPENDENCE-ISES 500kV Substation
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.