MISO-J2526
200 MW generation in Red River Parish, LA · In queue since September 2022 · Proposed COD October 2026
200 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-10-31
The proposed MISO-J2526 project is a 200 MW solar generation facility located in Red River Parish, Louisiana. The project, under development by CLECO POWER, entered the MISO interconnection queue on September 14, 2022, with a proposed commercial operation date of October 31, 2026. The point of interconnection is the Western Kraft-Layfield 230 kV substation.
The interconnection agreement for the project is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
LA
County
Red River Parish
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
CLECO POWER
Entity
MISO
Service Type
—
Point of Interconnection
Western Kraft-Layfield 230 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2526