50 MW generation in Graves, KY · In queue since September 2022 · Proposed COD March 2026
50 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
3y 6m
Schedule
2 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-03-01
MISO-J2541 is a proposed 50 MW solar generation project located in Graves County, Kentucky. The project is being developed by Big Rivers Electric Corporation and interconnected within the Midcontinent Independent System Operator (MISO) region. It entered the MISO interconnection queue on September 15, 2022, with a proposed commercial operation date of March 1, 2026. The project's interconnection status is currently in the Cluster Study phase, and the point of interconnection is the Bryan Road substation.
The proposed project consists of 50 MW of solar photovoltaic generation.
Generated from interconnection queue and public data sources
State
KY
County
Graves
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
BIG RIVERS ELECTRIC CORPORATION
Entity
MISO
Service Type
—
Point of Interconnection
Bryan Road
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.