MISO-J2550
75 MW storage in Yellow Medicine, MN · In queue since September 2022 · Proposed COD July 2030
75 MW
Capacity
1
Components
Battery
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2030
Total Duration
7y 10m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-07-18
MISO-J2550 is a proposed 75 MW battery storage project located in Yellow Medicine County, Minnesota. The project, which consists of 75 MW of battery capacity, is in the Midcontinent Independent System Operator (MISO) interconnection queue. Its point of interconnection is the Hazel Creek 345kV Substation.
The project entered the MISO queue on September 14, 2022, with a proposed commercial operation date of July 18, 2030. Its interconnection agreement status is currently listed as "Cluster Study". The utility associated with the project is Northern States Power Company.
Generated from interconnection queue and public data sources
State
MN
County
Yellow Medicine
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN STATES POWER COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Hazel Creek 345kV Substation
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Hazel Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2550