MISO-J2559
200 MW generation in Wood, WI · In queue since September 2022 · Proposed COD July 2029
200 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Total Duration
6y 10m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-07-18
The proposed MISO-J2559 project is a 200 MW solar generation facility located in Wood County, Wisconsin. The project was entered into the Midcontinent Independent System Operator (MISO) interconnection queue on September 14, 2022, with a proposed commercial operation date of July 18, 2029. The interconnecting utility is American Transmission Company, and the point of interconnection is the Arpin 345kV substation. The interconnection agreement status is listed as "In Progress (unknown study)".
The development project consists of 200 MW of solar photovoltaic generation. It is currently listed as an active project within the MISO queue.
Generated from interconnection queue and public data sources
State
WI
County
Wood
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Arpin 345kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Arpin Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.