MISO-J2561
153 MW generation in Yellow Medicine, MN · In queue since September 2022 · Proposed COD July 2030
153 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2030
Total Duration
7y 10m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-07-18
MISO-J2561 is a proposed solar generation project with a total capacity of 153 MW, located in Yellow Medicine County, Minnesota. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of September 15, 2022, and a proposed commercial operation date of July 18, 2030. The interconnecting utility is Northern States Power Company.
The project's interconnection status is currently in the Cluster Study phase. It will connect to the Hazel Creek 345kV Substation.
Generated from interconnection queue and public data sources
State
MN
County
Yellow Medicine
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN STATES POWER COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Hazel Creek 345kV Substation
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Hazel Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2561