MISO-J2567
240 MW storage in Ottawa, MI · In queue since September 2022 · Proposed COD April 2025
240 MW
Capacity
1
Components
Battery
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
2y 7m
Schedule
13 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-04-01
MISO-J2567 is a proposed 240 MW battery storage project located in Ottawa County, Michigan. The project, interconnected within the Midcontinent Independent System Operator (MISO) region, entered the MISO interconnection queue on September 15, 2022. Its proposed commercial operation date is April 1, 2025.
The interconnection agreement for MISO-J2567 is currently listed as "In Progress" with an unknown study. The project's point of interconnection (POI) is at the KENOWA substation. The queue data indicates the utility involved is METC.
Generated from interconnection queue and public data sources
State
MI
County
Ottawa
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
KENOWA
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Kenowa Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2567