MISO-J2571
176.6 MW generation in Tunica, MS · In queue since September 2022 · Proposed COD January 2024
176.6 MW
Capacity
1
Components
Wind
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
1y 4m
Schedule
27 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-01-31
MISO-J2571 is a proposed wind generation project with a total capacity of 176.6 MW located in Tunica County, Mississippi. The project is in the MISO interconnection queue, having entered on September 15, 2022, with a proposed commercial operation date of January 31, 2024. The interconnecting utility is Entergy Mississippi, LLC. and the project's interconnection status is currently in the Cluster Study phase.
The point of interconnection (POI) for MISO-J2571 is the New J866 Substation on the Batesville - Robert E. Ritchie 230 kV line. The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
MS
County
Tunica
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY MISSISSIPPI, LLC.
Entity
MISO
Service Type
—
Point of Interconnection
New J866 Substation (Batesville - Robert E. Ritchie 230 kV line)
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2571