MISO-J2572
200 MW storage in Hamilton, IN · In queue since September 2022 · Proposed COD April 2025
200 MW
Capacity
1
Components
Battery
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2025
Total Duration
2y 7m
Schedule
13 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-04-01
MISO-J2572 is a proposed 200 MW battery storage project located in Hamilton County, Indiana. The project, which is in the Indianapolis Power & Light Company service area, entered the MISO interconnection queue on September 15, 2022, with a proposed commercial operation date of April 1, 2025. Its interconnection status is currently in the Cluster Study phase.
The development project consists solely of battery storage, with a total capacity of 200 MW. The point of interconnection is the Noblesville STA - Hortonsville 345 kV line.
Generated from interconnection queue and public data sources
State
IN
County
Hamilton
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
INDIANAPOLIS POWER & LIGHT COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Noblesville STA - Hortonsville 345 kV line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2572