1 MW generation in MN · In queue since October 2012 · Proposed COD April 2013
1 MW
Capacity
1
Components
Other
13y 7m
In Queue
IA Executed
IA Status
COD target: 2013
Total Duration
6 months
Schedule
159 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Proposed COD: 2013-04-01
The proposed MISO-J258 project is a 1 MW generation project located in Minnesota. The project, categorized as "Other" technology, entered the Midcontinent Independent System Operator (MISO) interconnection queue on October 30, 2012, with a proposed commercial operation date of April 1, 2013.
The interconnection agreement for the project has been executed. The point of interconnection is the Melrose East 69kV Substation.
Generated from interconnection queue and public data sources
State
MN
County
—
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
—
Point of Interconnection
Melrose East 69kV Substation
Data Source
LBNL
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- NSP.MRES_5.AZ
- POI Substation
- East Melrose Substation