Project MISO-J2587 — Project Summary

Queue ID
MISO-J2587
Capacity
200 MW
Technology
Battery
Status
active
Location
Vigo, IN
Region
MISO
Developer
IA Status
Cluster Study

MISO-J2587

MISO-J2587BetaActiveBatteryMISOLBNL + Live

200 MW storage in Vigo, IN · In queue since September 2022 · Proposed COD April 2025

200 MW

Capacity

1

Components

Battery

3y 8m

In Queue

Cluster Study

IA Status

COD target: 2025

Interconnection

Total Duration

2y 7m

Schedule

13 months past proposed COD

Impact Study25%
Queue EntrySep 15, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-04-01

About

MISO-J2587 is a proposed 200 MW battery storage project located in Vigo County, Indiana. The project, which is in the Duke Energy Indiana service area, consists of a single 200 MW battery component.

The project is currently active in the MISO interconnection queue, with an entry date of September 15, 2022. Its proposed commercial operation date is April 1, 2025. The interconnection request is currently in the Cluster Study phase.

Generated from interconnection queue and public data sources

Project Details

State

IN

County

Vigo

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

DUKE ENERGY INDIANA

Entity

MISO

Service Type

Point of Interconnection

Sugar Creek - Cayuga 345 kV Transmission Line

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
MISO
Trading Hub
INDIANA.HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project MISO-J2587