MISO-J2587
200 MW storage in Vigo, IN · In queue since September 2022 · Proposed COD April 2025
200 MW
Capacity
1
Components
Battery
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2025
Total Duration
2y 7m
Schedule
13 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-04-01
MISO-J2587 is a proposed 200 MW battery storage project located in Vigo County, Indiana. The project, which is in the Duke Energy Indiana service area, consists of a single 200 MW battery component.
The project is currently active in the MISO interconnection queue, with an entry date of September 15, 2022. Its proposed commercial operation date is April 1, 2025. The interconnection request is currently in the Cluster Study phase.
Generated from interconnection queue and public data sources
State
IN
County
Vigo
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
DUKE ENERGY INDIANA
Entity
MISO
Service Type
—
Point of Interconnection
Sugar Creek - Cayuga 345 kV Transmission Line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- MEDIUM