MISO-J2601
200 MW storage in Wabasha, MN · In queue since September 2022 · Proposed COD June 2026
200 MW
Capacity
1
Components
Battery
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-30
MISO-J2601 is a proposed 200 MW battery storage project located in Wabasha County, Minnesota. The project, which consists entirely of battery storage, is in the Midcontinent Independent System Operator (MISO) interconnection queue. Its queue entry date is September 15, 2022, with a proposed commercial operation date of June 30, 2026. The project's interconnection agreement status is currently in the Cluster Study phase.
The project is being proposed within the service territory of Northern States Power Company. The point of interconnection is the North Rochester to Briggs Road 345 kV Tap. The project is listed as active in the MISO queue.
Generated from interconnection queue and public data sources
State
MN
County
Wabasha
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN STATES POWER COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
North Rochester to Briggs Road 345 kV Tap
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2601