MISO-J2607
200 MW storage in Montgomery, IL · In queue since September 2022 · Proposed COD June 2026
200 MW
Capacity
1
Components
Battery
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-30
MISO-J2607 is a proposed 200 MW battery storage project located in Montgomery County, Illinois. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of September 15, 2022, and a proposed commercial operation date of June 30, 2026. The interconnecting utility is Ameren Illinois.
The project's interconnection status is currently in the Cluster Study phase. The point of interconnection (POI) is the Redhawk 138 kV - MTEP Project (17976).
Generated from interconnection queue and public data sources
State
IL
County
Montgomery
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Redhawk 138 kV - MTEP Project (17976)
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2607