MISO-J2608
160 MW generation in Stevens, MN · In queue since September 2022 · Proposed COD September 2026
160 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
4 years
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-01
The proposed MISO-J2608 project is a 160 MW solar generation project located in Stevens County, Minnesota. The project is being developed within the Great River Energy service territory. It consists of 160 MW of solar photovoltaic generation.
The project is currently active in the MISO interconnection queue, having entered the queue on September 14, 2022. Its proposed commercial operation date is September 1, 2026. The project's interconnection status is currently in the Cluster Study phase and its point of interconnection is the Hancock 161kV Substation.
Generated from interconnection queue and public data sources
State
MN
County
Stevens
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
GREAT RIVER ENERGY
Entity
MISO
Service Type
—
Point of Interconnection
Hancock 161kV Substation
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- DECO.HNKP111
- POI Substation
- Hancock Substation