MISO-J2613
300 MW generation in Jackson, AR · In queue since September 2022 · Proposed COD October 2025
300 MW
Capacity
1
Components
Wind
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 1m
Schedule
7 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-10-01
MISO-J2613 is a proposed 300 MW wind generation project located in Jackson County, Arkansas. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an initial queue entry date of September 15, 2022. The proposed commercial operation date is October 1, 2025. Entergy Arkansas is listed as the utility.
The interconnection agreement for MISO-J2613 is currently listed as "In Progress (unknown study)". The point of interconnection is the Independent - Holland Bottom 500kV substation.
Generated from interconnection queue and public data sources
State
AR
County
Jackson
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY ARKANSAS
Entity
MISO
Service Type
—
Point of Interconnection
Independent - Holland Bottom 500kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- ALTE.ONIONRIV
- POI Substation
- Holland