MISO-J2614
200 MW generation in Henry, IL · In queue since September 2022 · Proposed COD September 2026
200 MW
Capacity
1
Components
Wind
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
4 years
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-30
MISO-J2614 is a proposed 200 MW wind generation project located in Henry County, Illinois. The project is in the MISO interconnection queue, having entered on September 15, 2022, with a proposed commercial operation date of September 30, 2026. The interconnecting utility is Ameren Illinois.
The project's interconnection status is currently in the Cluster Study phase. The point of interconnection (POI) is the Oak Grove 161 kV substation.
Generated from interconnection queue and public data sources
State
IL
County
Henry
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Oak Grove 161 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MEC.OAKGRM.MVP
- POI Substation
- Oak Grove Substation