MISO-J2618
100 MW storage in Macomb, MI · In queue since September 2022 · Proposed COD September 2026
100 MW
Capacity
1
Components
Battery
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4 years
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-30
MISO-J2618 is a proposed 100 MW battery storage project located in Macomb County, Michigan. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an initial queue entry date of September 15, 2022. The proposed commercial operation date is September 30, 2026. The project's interconnection agreement status is listed as "In Progress (unknown study)" and the interconnecting utility is ITC.
The project, sponsored by an unknown developer, consists of 100 MW of battery storage capacity. The point of interconnection (POI) is the Lenox 120kV substation. The project is currently listed as active within the MISO queue.
Generated from interconnection queue and public data sources
State
MI
County
Macomb
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC
Entity
MISO
Service Type
—
Point of Interconnection
Lenox 120kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Lenox Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2618