MISO-J2619
140 MW hybrid in Montcalm, MI · In queue since September 2022 · Proposed COD September 2026
140 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4 years
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-30
MISO-J2619 is a proposed 140 MW hybrid solar and battery energy storage project located in Montcalm County, Michigan. The project, which consists of 140 MW of solar generation, is in the Midcontinent Independent System Operator (MISO) interconnection queue. Its queue entry date is September 15, 2022, and the proposed commercial operation date is September 30, 2026.
The interconnection agreement status for MISO-J2619 is listed as "In Progress (unknown study)". The designated point of interconnection (POI) is the Kenowa to Nelson Rd. 345kV line. The interconnecting utility is METC.
Generated from interconnection queue and public data sources
State
MI
County
Montcalm
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
Kenowa to Nelson Rd. 345kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2619