MISO-J2639
105.8 MW generation in Bradley, AR · In queue since September 2022 · Proposed COD June 2025
105.8 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
2y 9m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-01
MISO-J2639 is a proposed solar generation project located in Bradley County, Arkansas, within the Entergy Arkansas service area. The project, with a total capacity of 105.8 MW, is currently active in the Midcontinent Independent System Operator (MISO) interconnection queue. The queue entry date is September 9, 2022, and the proposed commercial operation date is June 1, 2025.
The interconnection agreement (IA) status is listed as "In Progress (unknown study)". The point of interconnection (POI) is the AECC Hermitage South - Hilo 115.0kV substation.
Generated from interconnection queue and public data sources
State
AR
County
Bradley
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY ARKANSAS
Entity
MISO
Service Type
—
Point of Interconnection
AECC HERMITAGE SOUTH - HILO 115.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- HIGH
- POI Substation
- South
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.