MISO-J2654
180 MW generation in Clinton, IN · In queue since September 2022 · Proposed COD July 2026
180 MW
Capacity
1
Components
Wind
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-07-01
MISO-J2654 is a proposed wind generation project with a total capacity of 180 MW. The project is located in Clinton County, Indiana, and is being developed within the MISO region. The interconnection request was entered into the MISO queue on September 14, 2022, with a proposed commercial operation date of July 1, 2026. Duke Energy Indiana is the utility associated with the project.
The project's interconnection status is currently in the Cluster Study phase. The point of interconnection (POI) is on a tap on the Frankfort - New London 230 kV Line.
Generated from interconnection queue and public data sources
State
IN
County
Clinton
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
DUKE ENERGY INDIANA
Entity
MISO
Service Type
—
Point of Interconnection
Tap on Frankfort - New London 230 kV Line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2654