MISO-J2657
200 MW storage in White, IN · In queue since September 2022 · Proposed COD May 2027
200 MW
Capacity
1
Components
Battery
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2027
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-05-01
MISO-J2657 is a proposed 200 MW battery storage project located in White County, Indiana. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on September 15, 2022. Northern Indiana Public Service Company is the utility associated with the project. The proposed commercial operation date is May 1, 2027, and the project's interconnection agreement status is currently in the Cluster Study phase.
The development project consists solely of battery storage, with a total capacity of 200 MW. The point of interconnection is the Reynolds - Burr Oak 345 kV Line.
Generated from interconnection queue and public data sources
State
IN
County
White
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN INDIANA PUBLIC SERVICE COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Reynolds - Burr Oak 345 kV Line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2657