MISO-J2667
200 MW generation in Sanilac, MI · In queue since September 2022 · Proposed COD November 2025
200 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 2m
Schedule
6 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-11-01
MISO-J2667 is a proposed solar generation project with a total capacity of 200 MW, located in Sanilac County, Michigan. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on September 14, 2022. The proposed commercial operation date is November 1, 2025. The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Greenwood-Rapson 345 kV Transmission Line, and the interconnecting utility is ITC.
The development project consists solely of solar generation, with the full 200 MW capacity attributed to solar photovoltaic technology. The project is located within the MISO region.
Generated from interconnection queue and public data sources
State
MI
County
Sanilac
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC
Entity
MISO
Service Type
—
Point of Interconnection
Greenwood-Rapson 345 kV Transmission Line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.