MISO-J2673
225 MW generation in Clare, MI · In queue since September 2022 · Proposed COD November 2025
225 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2025
Total Duration
3y 2m
Schedule
6 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-11-01
MISO-J2673 is a proposed solar generation project located in Clare County, Michigan, with a total capacity of 225 MW. The project, interconnected within the Midcontinent Independent System Operator (MISO) region, entered the MISO queue on September 14, 2022. Its proposed commercial operation date is November 1, 2025. The interconnection status is currently in the Cluster Study phase.
The project, which consists solely of solar generation, is connected to the grid at the Bard Rd to Warren 138 kV point of interconnection. The utility involved is METC, and the entity responsible for the interconnection is MISO. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
MI
County
Clare
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
Bard Rd to Warren 138 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2673