MISO-J2675
170 MW generation in Gladwin, MI · In queue since September 2022 · Proposed COD November 2025
170 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 2m
Schedule
6 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-11-01
MISO-J2675 is a proposed 170 MW solar generation project located in Gladwin County, Michigan. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of September 14, 2022, and a proposed commercial operation date of November 1, 2025. The interconnecting utility is METC.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the BARD ROAD - GALLAGHER 138 KV substation.
Generated from interconnection queue and public data sources
State
MI
County
Gladwin
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
BARD ROAD - GALLAGHER 138 KV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM