MISO-J2676
200 MW generation in Huron, MI · In queue since September 2022 · Proposed COD November 2025
200 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2025
Total Duration
3y 2m
Schedule
6 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-11-01
MISO-J2676 is a proposed 200 MW solar generation project located in Huron County, Michigan. The project is interconnected within the Midcontinent Independent System Operator (MISO) queue, having entered the queue on September 14, 2022. The proposed commercial operation date is November 1, 2025. The interconnection status is currently in the Cluster Study phase.
The project, which is interconnected with ITC, consists of 200 MW of solar photovoltaic generation. The point of interconnection is the Rapson-Stein 345kV substation. The project is listed as active within the MISO queue.
Generated from interconnection queue and public data sources
State
MI
County
Huron
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC
Entity
MISO
Service Type
—
Point of Interconnection
Rapson -Stein 345kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2676