MISO-J2679
100 MW generation in Livingston, MI · In queue since September 2022 · Proposed COD April 2027
100 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-15
MISO-J2679 is a proposed 100 MW solar generation project located in Livingston County, Michigan. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on September 14, 2022. The proposed commercial operation date is April 15, 2027. The project's interconnection agreement status is listed as "In Progress (unknown study)".
The project is being developed within the ITC utility territory and interconnects at the COLFAX to Madrid 120 kV point of interconnection.
Generated from interconnection queue and public data sources
State
MI
County
Livingston
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC
Entity
MISO
Service Type
—
Point of Interconnection
COLFAX to Madrid 120 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2679