MISO-J2685
120 MW generation in Sharkey, MS · In queue since September 2022 · Proposed COD January 2026
120 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 4m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-01-01
MISO-J2685 is a proposed solar generation project with a total capacity of 120 MW, located in Sharkey County, Mississippi. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of September 14, 2022, and a proposed commercial operation date of January 1, 2026. The interconnecting utility is Entergy Mississippi, LLC.
The interconnection agreement (IA) status for MISO-J2685 is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Rolling Fork 115 kV Substation.
Generated from interconnection queue and public data sources
State
MS
County
Sharkey
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY MISSISSIPPI, LLC.
Entity
MISO
Service Type
—
Point of Interconnection
Rolling Fork 115 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- Rolling Fork Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2685