MISO-J2686
150 MW generation in Muscatine, IA · In queue since September 2022 · Proposed COD September 2026
150 MW
Capacity
1
Components
Wind
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
4 years
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-30
MISO-J2686 is a proposed 150 MW wind energy project in Muscatine County, Iowa. The project, developed by MidAmerican Energy Co., is currently active in the Midcontinent Independent System Operator (MISO) interconnection queue. It entered the queue on September 15, 2022, with a proposed commercial operation date of September 30, 2026.
The project's interconnection status is currently in the Cluster Study phase. The point of interconnection (POI) is the Walcott 345 kV substation. The project has appeared in recent news coverage regarding renewable energy development in the region.
Generated from interconnection queue and public data sources
State
IA
County
Muscatine
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
MIDAMERICAN ENERGY CO.
Entity
MISO
Service Type
—
Point of Interconnection
Walcott 345 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Walcott Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.