MISO-J2690
500 MW hybrid in Washington, IL · In queue since September 2022 · Proposed COD April 2027
500 MW
Capacity
1
Components
Wind
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2027
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-15
MISO-J2690 is a proposed 500 MW hybrid wind and battery project located in Washington County, Illinois. The project, which consists of 500 MW of wind generation, is in the MISO interconnection queue as of September 15, 2022, with a proposed commercial operation date of April 15, 2027. The interconnecting utility is Ameren Illinois.
The project's interconnection status is currently in the Cluster Study phase.
Generated from interconnection queue and public data sources
State
IL
County
Washington
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Other_
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.