MISO-J2691
500 MW hybrid in Bollinger, MO · In queue since September 2022 · Proposed COD April 2027
500 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2027
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-15
MISO-J2691 is a proposed 500 MW hybrid Solar+Battery project located in Bollinger County, Missouri. The project, which also lists Wind as a technology detail, consists of 500 MW of solar capacity. It is currently active in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on September 15, 2022, with a proposed commercial operation date of April 15, 2027. The interconnection utility is Ameren Missouri, and the point of interconnection is Rush-Baldwin-4585 345 kV. The project's interconnection agreement status is currently in the Cluster Study phase.
Generated from interconnection queue and public data sources
State
MO
County
Bollinger
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN MISSOURI
Entity
MISO
Service Type
—
Point of Interconnection
Rush-Baldwin-4585 345 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.