MISO-J2694
500 MW hybrid in Christian, IL · In queue since September 2022 · Proposed COD April 2027
500 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2027
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-15
MISO-J2694 is a proposed 500 MW hybrid Solar+Battery project located in Christian County, Illinois. The project, which includes a 500 MW solar component, is in the MISO interconnection queue as of September 15, 2022, with a proposed commercial operation date of April 15, 2027. The interconnecting utility is Ameren Illinois.
The project's interconnection status is currently in the Cluster Study phase. The point of interconnection is the 7COFFEEN-7PANA 345 kV line.
Generated from interconnection queue and public data sources
State
IL
County
Christian
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
7COFFEEN-7PANA 345 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.