MISO-J2704
500 MW generation in Ouachita Parish, LA · In queue since September 2022 · Proposed COD April 2027
500 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-15
MISO-J2704 is a proposed solar generation project with a total capacity of 500 MW, located in Ouachita Parish, Louisiana. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered on September 14, 2022. The proposed commercial operation date is April 15, 2027.
The interconnection agreement (IA) status is listed as "In Progress (unknown study)". The project's point of interconnection (POI) is the Baxter Wilson SES SWYD - Perryville 500 500 kV. The utility is Entergy Louisiana.
Generated from interconnection queue and public data sources
State
LA
County
Ouachita Parish
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY LOUISIANA
Entity
MISO
Service Type
—
Point of Interconnection
BAXTER WILSON SES SWYD - PERRYVILLE 500 500 kV (181.1,503.0)
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.