MISO-J2714
162 MW generation in St. Landry Parish, LA · In queue since September 2022 · Proposed COD April 2027
162 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-15
MISO-J2714 is a proposed solar generation project with a total capacity of 162 MW, located in St. Landry Parish, Louisiana. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on September 14, 2022. CLECO POWER is the listed utility. The proposed commercial operation date is April 15, 2027, and the interconnection agreement status is listed as "In Progress (unknown study)".
The development project consists solely of solar photovoltaic generation, with the entire 162 MW capacity attributed to solar technology. The point of interconnection (POI) is the EUNICE 138 kV substation.
Generated from interconnection queue and public data sources
State
LA
County
St. Landry Parish
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
CLECO POWER
Entity
MISO
Service Type
—
Point of Interconnection
EUNICE 138 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- Lake Eunice Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2714