MISO-J2715
120 MW generation in Acadia Parish, LA · In queue since September 2022 · Proposed COD April 2027
120 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-15
MISO-J2715 is a proposed solar generation project with a total capacity of 120 MW, located in Acadia Parish, Louisiana. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on September 14, 2022. The proposed commercial operation date is April 15, 2027.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The interconnecting utility is Entergy Louisiana. The point of interconnection (POI) is the COLONIAL ACADEMY CO 138 kV substation.
Generated from interconnection queue and public data sources
State
LA
County
Acadia Parish
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY LOUISIANA
Entity
MISO
Service Type
—
Point of Interconnection
COLONIAL ACADEMY CO 138 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2715