MISO-J2720
200 MW generation in Yazoo, MS · In queue since September 2022 · Proposed COD April 2025
200 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
2y 7m
Schedule
12 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-04-25
MISO-J2720 is a proposed solar generation project with a total capacity of 200 MW, located in Yazoo County, Mississippi. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on September 14, 2022. The proposed commercial operation date is April 25, 2025. The interconnecting utility is Entergy Mississippi, LLC.
The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Midway SS (CE) - Yazoo City SS 115 kV substation. Recent news coverage of the project is available.
Generated from interconnection queue and public data sources
State
MS
County
Yazoo
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY MISSISSIPPI, LLC.
Entity
MISO
Service Type
—
Point of Interconnection
Midway SS (CE) - Yazoo City SS 115 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- Midway
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2720