MISO-J2728
150 MW storage in Freeborn, MN · In queue since September 2022 · Proposed COD July 2025
150 MW
Capacity
1
Components
Battery
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2025
Total Duration
2y 10m
Schedule
9 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-07-24
MISO-J2728 is a proposed 150 MW battery storage project located in Freeborn County, Minnesota. The project, interconnected within the Midcontinent Independent System Operator (MISO) region, entered the MISO interconnection queue on September 14, 2022. Its proposed commercial operation date is July 24, 2025. The project's interconnection agreement status is currently in the Cluster Study phase, and the point of interconnection is Glenworth.
The development project consists solely of battery storage, with a total capacity of 150 MW. The interconnecting utility is ITC Midwest.
Generated from interconnection queue and public data sources
State
MN
County
Freeborn
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC MIDWEST
Entity
MISO
Service Type
—
Point of Interconnection
Glenworth
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2728