MISO-J2737
180 MW generation in Sabine Parish, LA · In queue since September 2022 · Proposed COD September 2026
180 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4 years
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-30
MISO-J2737 is a proposed solar generation project with a total capacity of 180 MW. The development is located in Sabine Parish, Louisiana, and is being proposed by CLECO POWER. The project consists of 180 MW of solar photovoltaic generation.
The project is currently active in the MISO interconnection queue, with an initial queue entry date of September 15, 2022. The proposed commercial operation date is September 30, 2026. The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Hartburg - AEP Layfield 500kV Line.
Generated from interconnection queue and public data sources
State
LA
County
Sabine Parish
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
CLECO POWER
Entity
MISO
Service Type
—
Point of Interconnection
Hartburg - AEP Layfield 500kV Line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- AEP
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2737