MISO-J2738
128 MW hybrid in Rock Island, IL · In queue since September 2022 · Proposed COD February 2025
128 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2025
Total Duration
2y 5m
Schedule
15 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-02-01
MISO-J2738 is a proposed 128 MW hybrid solar and battery energy storage project located in Rock Island County, Illinois. The project, which consists of 128 MW of solar generation, is being developed within the Midcontinent Independent System Operator (MISO) region and is interconnected to the MIDAMERICAN ENERGY CO. utility grid at the point of interconnection SUB 17.
The project entered the MISO interconnection queue on September 15, 2022, and has a proposed commercial operation date of February 1, 2025. Its interconnection status is currently in the Cluster Study phase. The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
IL
County
Rock Island
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
MIDAMERICAN ENERGY CO.
Entity
MISO
Service Type
—
Point of Interconnection
SUB 17
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Sub 91
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.