MISO-J2739
100 MW generation in Ohio, KY · In queue since September 2022 · Proposed COD September 2026
100 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
4 years
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-01
The MISO-J2739 proposed project is a 100 MW solar generation facility located in Ohio County, Kentucky. The project, under consideration by Big Rivers Electric Corporation, entered the Midcontinent Independent System Operator (MISO) interconnection queue on September 14, 2022, with a proposed commercial operation date of September 1, 2026. Its interconnection status is currently in the Cluster Study phase.
The proposed project consists of 100 MW of solar photovoltaic generation. It is interconnected to the grid at the 5WLSNBR 161 kV point of interconnection.
Generated from interconnection queue and public data sources
State
KY
County
Ohio
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
BIG RIVERS ELECTRIC CORPORATION
Entity
MISO
Service Type
—
Point of Interconnection
5WLSNBR 161 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2739