MISO-J2740
150 MW generation in Sunflower, MS · In queue since September 2022 · Proposed COD September 2026
150 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4 years
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-01
MISO-J2740 is a proposed solar generation project located in Sunflower County, Mississippi, with a total capacity of 150 MW. The project, which is in the Midcontinent Independent System Operator (MISO) interconnection queue, was entered on September 13, 2022, and has a proposed commercial operation date of September 1, 2026. The interconnecting utility is Entergy Mississippi, LLC.
The interconnection agreement (IA) status for MISO-J2740 is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Delta SWYD - Shelby SS 115.0kV substation.
Generated from interconnection queue and public data sources
State
MS
County
Sunflower
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY MISSISSIPPI, LLC.
Entity
MISO
Service Type
—
Point of Interconnection
DELTA SWYD - SHELBY SS 115.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2740