MISO-J2742
100 MW generation in White, AR · In queue since September 2022 · Proposed COD September 2026
100 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4 years
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-01
MISO-J2742 is a proposed solar generation project located in White County, Arkansas, within the Midcontinent Independent System Operator (MISO) region. The project, with a total capacity of 100 MW, is being developed in the Entergy Arkansas service area. It consists of 100 MW of solar photovoltaic generation.
The project entered the MISO interconnection queue on September 13, 2022, and has a proposed commercial operation date of September 1, 2026. Its interconnection agreement status is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is at the BEEBE substation.
Generated from interconnection queue and public data sources
State
AR
County
White
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY ARKANSAS
Entity
MISO
Service Type
—
Point of Interconnection
BEEBE
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Beebe Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2742